HC Deb 24 February 1984 vol 54 c648W
Mr. Rooker

asked the Secretary of State for Transport if he will make a statement on the progress of the bearing replacements at Bromford viaduct on the M6 motorway; if the work will be completed on time; and whether it will be at the tender cost.

Mrs. Chalker

The contract for bearing plinth replacements is due for completion at the end of March, but it seems likely that the contractor will overrun this by several weeks. The final cost will depend on the engineer's decision concerning any claims the contractor may submit. My Department has been advised that the contract sum is likely to increase from the tender sum of £509,793 to £790,232 due to an increase in the amount of cold weather working.