§ Mr. McKelveyasked the Secretary of State for Energy what is the average difference in construction costs between coal and nuclear power stations of the same size.
§ Mr. John MooreOn the basis of information supplied by the CEGB, I understand that its estimate of capital costs of generating plant at March 1982 prices, together with the expected output in each case, is as follows:
Type of Station Output (MWso) Cost (£) New coal 1,875 1,245 PWR* 1,110 1,147 AGR* 1,230 1,590 * Excluding initial fuel which for the PWR would be £59 million and for the AGR £109 million.