HC Deb 14 December 1983 vol 50 c473W
Mr. Trotter

asked the Secretary of State for Defence whether he will give details of the extent to which each

Ship Refitting dockyard Start date Completion date Outturn* £ million
Batch 1A
Leander Devonport 8 June 1970 12 January 1973 7.587
Ajax Devonport 19 October 1970 7 February 1974 8.269
Galatea Devonport 4 October 1971 6 September 1974 9.217
Batch 1B
Aurora Chatham 4 December 1972 27 February 1976 15.580
Naiad Devonport 15 January 1973 20 June 1975 10.410
Euryalus Devonport 7 May 1973 12 March 1976 12.127
Arethusa Portsmouth 10 September 1973 7 April 1977 16.585
Dido Devonport 7 July 1975 27 October 1978 23.006
Batch 2A
Cleopatra Devonport 23 July 1973 19 December 1975 13.820
Phoebe Devonport 5 August 1974 28 April 1977 18.204
Sirius Devonport 10 March 1975 10 February 1978 21.598
Minerva Chatham 1 December 1975 11 April 1979 31.575
Batch 2B
Argonaut Devonport 23 February 1976 28 March 1980 30.262
Danae Devonport 1 August 1977 8 April 1981 39.279
Penelope Devonport 30 January 1978 15 January 1982 47.687
Batch 3A
Andromeda Devonport 3 January 1978 6 February 1981 59.990
Charybdis Devonport 25 June 1979 16 July 1982 61.581
Jupiter Devonport 28 January 1980 14 October 1983 †68.348
Hermione Chatham/Devonport 14 January 1980 8 December 1983 †79.692
Scylla Devonport 10 November 1980 Mid 1985 †79.278
* At current prices for the year in question announced in Cmnd. 8288 in 1981.
† Latest estimate.

Note:

In accordance with decisions, the remaining Batch 3 ships Achilles, Diomede, Apollo and Ariadne will not be modernised. Juno is currently being converted at Rosyth to serve as a navigational training ship.