HC Deb 05 December 1983 vol 50 c80W
Mr. William Ross

asked the Secretary of State for Northern Ireland what is now the estimated total cost of the Madams bank bridge, including the costs of providing the necessary approach roads which would not have been required if the bridge were not constructed.

Mr. Chris Patten

£26.9 million.

Mr. William Ross

asked the Secretary of State for Northern Ireland when he now expects construction work on the Madams bank bridge to be completed; and what was the original completion date.

Mr. Chris Patten

Early spring 1984. The original completion date for the contract was 2 December 1983.