HC Deb 02 December 1983 vol 49 cc626-7W
Mr. Corbett

asked the Secretary of State for Transport whether he will list in the Official Report all current road works on the MI northbound and southbound between junctions 8 and 19; when these are expected to be completed; when they were due to be completed and at what cost against the original estimate.

Mrs. Chalker

The information requested is as follows:

when these are expected to be completed; when they were due to be completed; and at what cost against the original estimate.

Mrs. Chalker

The information requested is as follows:

M6 Location Works in Progress Programmed Completion Date Expected Completion Original Estimated Cost Current Estimated Cost
Junctions 5–6 Renewal of bearing plinths on Bromford Viaduct March 1984 March 1984 £510,000 £510,000
5–6 Repairs to hard shoulder verge on northbound carriageway December 1983 December 1983 £5,000 £5,000
6–7 Repairs to parapst rail on southbound carriageway December 1983 December 1983 £6,000 £6,000