HC Deb 02 December 1983 vol 49 c629W
Mr. Dalyell

asked the Secretary of State for the Environment what discussions he has had with Cenargo Limited about the two breakdowns of its ship, the Merchant Providence, resulting in the late arrival of equipment at Port Stanley; and if he will make a statement.

Sir George Young

None. Shipping arrangements are the responsibility of the contractor, the Laing-Mowlem-Amey Roadstone construction joint venture. The Merchant Providence is in position in the Falklands and will provide an offloading facility during the period of construction of the new Mount Pleasant airfield. The project is still on schedule to meet the completion dates referred to by my right hon. Friend the Secretary of State for Defence in his statement of 27 June 1983. —[Vol. 44, c. 345.]

Back to