HC Deb 12 May 1982 vol 23 cc286-9W
Mr. Roy Hughes

asked the Secretary of State for Transport what is the actual expenditure in 1981–82 on each scheme listed in table 1 of the appendix to 1981–82 Class VI, 1 section of the Supply Estimates; and how this compares with the estimated provisions in each case.

Mrs. Chalker

The information is as follows:

New Construction and Improvement: Motorways and Trunk Roads
Supply Estimate Provision 1981–82 Actual Expenditure 1981–82
£'000 £'000
Motorways
Schemes in progress (contracts let by 31 October 1980)
M1 London-Yorkshire Motorway
Breakspear-Berry grove 11,791 10,257
M20 Mid Kent Motorway
Ashford-Folkestone 7,083 12,983
M25 London Outer Orbital Motorway
Yeoveny-Airport Spur 10,211 10,060
A10-M11 33,452 27,646
A12-A13 25,047 23,574
M11-A12 22,129 19,979
A111-A10 5,668 8,749
M63 Manchester Outer Ring Road
Stockport East/West Bypass, Stage 2 3,473 3,800
Stockport East/West Bypass, Stages 4/5 8,402 9,892
M67 Hyde and Demon By-pass Motorway
Denton Relief Road, Stage 1 3,228 3,650
M531 Ellesmere Port Motorway
Southern Extension (100 per cent. Grant Scheme) 6,540 6,709
M602 Salford-Eccles Motorway
Extension to Salford Docks (100 per cent. Grant Scheme) 9,170 8,146
Proposals to start (contracts let after 31 October 1980)
M25 London Outer Orbital Motorway
Chertsey to Reigate-Chertsey to Wisley Section 10,115 5,684
M27 South Coast Motorway
Chilworth to Hedge End 9,836 2,331
M54 Telford Motorway
Telford-M6 15,866 11,543
M65 Calder Valley Route
Hyndburn-Bumley (including Accrington Easterly Bypass (Northern Section) 13,753 10,255
TRUNK ROADS
Schemes in progress (contracts let by 31 October 1980)
Proposed Colchester-Harwich Road
Colchester Eastern and Elmstead Market Bypass (Essex) 9,724 11,313
London-Tilbury Road
Mar Dyke-East of Grays (Essex) 9,733 10,369
East of Snaith-Sunderland Road
Billingham Diversion (Cleveland) 7,142 7,846
London-Canterbury-Dover Road
Canterbury Southern Bypass (Kent) 3,168 3,768
Winchester-Preston Road
Kingsworthy-Bullington (Sutton Scotney Bypass) (Hants.) 5,664 5,545
Felixstowe-Weedon and London-Yarmouth Roads
Ipswich Southern and Eastern Bypass (Suffolk) 22,416 22,495

Supply Estimate Provision 1981–82 Actual Expenditure 1981–82
£'000 £'000
Manchester-Burnley Road
Haslingdon Bypass (Lancashire) 5,982 5,891
Girton-Godmanchester Road
Bar Hill-Godmanchester (Cambridgeshire) 3,904 1,064
Kendal-Doncaster Road
Skipton Western and Northern Bypasses (N. Yorkshire) 5,366 5,263
Proposals to start (contracts let after 31 October 1980)
Sheffield-Grimsby Road
Brigg-Grimsby (Humberside) 6,741 8,811
London-Carlisle-Glasgow-Inverness Road
Derby Ring Road 4,047 2,245
London-Fishguard Road
Gloucester Northern Bypass 3,812 4,746
Manchester-Bumley Road
Accrington Eastern Bypass (Southern Section) 101
Liverpool-Leeds-Hull Road
South Docks Road, Hull (Humberside) 4,945 4,252
Total 288,509 268,866

The estimates themselves included on off-setting allowance of £10.9 million for work which might not in the events be undertaken in the year, though this covered smaller schemes as well as those costing over £10 million each.

Mr. Roy Hughes

asked the Secretary of State for Transport if he will update with his latest estimates table 2 of the appendix to the 1981–82 Class VI, 1 of the 1981–82 Supply estimates; and if he will publish on the same basis similar figures for 1982–83.

Mrs. Chalker

The information is attached:—

The following is an updated version of table 2 of the appendix to Class VI, 1 of the 1981–82 Supply Estimates:
Motorways and Trunk Roads Current estimate of total cost Expenditure to 31 March 1981 Actual expenditure in 1981–82
£000 £000 £000
Work in progress at 1 April 1981 on schemes costing more than £1million 826,713 322,740 246,051
New schemes proposed to start in 1981–82 costing more than £1million 439,212 13,206 85,758
Residual expenditure on completed schemes and preliminary expenditure on land, etc. for future schemes costing £1 million or more 48,819
TOTAL 1,265,925 335,946 380,628

Motorways and Trunk Roads Current estimate of total cost Expenditure to 31 March 1981 Actual expenditure in 1981–82
£000 £000 £000
Other schemes costing less than £1 million each 25,259
Less: Allowance for services which may not be carried out in the year
TOTAL—Subhead A1 405,887

Notes:

(1) The column giving the estimated requirements at survey prices has been omitted because public expenditure figures are now presented solely on a cash basis.

(2) The expenditure figures for 1981–82 are provisional.

The following table gives similar figures for 1982–83
Motorways and Trunk Roads Current estimate of total cost Expenditure to 31 March 1982 Actual expenditure in 1982–83
£000 £000 £000
Work in progress at 1 April 1982 on schemes costing more than £1million 747,622 324,783 265,826
New schemes proposed to start in 1982–83 costing more than £1million 636,088 12,978 116,344
Residual expenditure on completed schemes and preliminary expenditure on land, etc. for future schemes costing £1 million or more 68,895
TOTAL 1,383,710 37,761 451,065
Other schemes costing less than £1 million each 33,489
Less: Allowance for services which may not be carried out in the year 10,000
Total—Subhead A1 474,554

Notes:

See note 1 to the previous table.