HC Deb 09 March 1981 vol 1000 c241W
Mr. John Morris

asked the Secretary of State for Wales which road schemes in Wales have been delayed as a result of Government policy, identifying them by name and length of delay.

Mr. Wyn Roberts

I refer the right hon. and learned Gentleman to my hon. Friend's answer to his question of 18 February.—fVol 999, c. 147.] The following schemes were delayed in 1980–81 to keep within the cash limit for the year but are now proceeding:

Name of Scheme Length of delay
A470: Improvement at Carno (Contract E) 7 months
A483: Maeslan Bends, Llanbister 7 months
A494:Improvement at Iwerddon 7½months
A494: Improvement East of junction with B5430 near Llanferres 8 months

Non-trunk road schemes are the responsibility of local authorities.