HC Deb 15 May 1980 vol 984 c561W
Mr. Roy Hughes

asked the Secretary of State for Wales (1) if he will list in the Official Report all motorway and trunk road schemes with a total cost of over £3 million in the same format as the appendix

Estimated requirements for 1980–81
Schemes Year of authorisation to year of completion Current estimate of total cost £'000 Probable expenditure to 31 March 1980 £'000 At 1980 survey prices £'000 At outturn prices £'000
Schemes in Progress: Contracts let by 31 October 1979
A40/A470 Brecon Southern and Eastern By-Pass 1978–80 9,043 6,850 880 982
A40 St. Clears By-Pass 1977–79 4,150 3,587 35 39
A40 Black Bridge and Pont Loerig 1978–80 1,375 1,305 45 50
A40 Cefn Brynich, including Cross Roads 1978–80 707 577 110 124
A40 Treffgarne Bridge 1978–80 800 678 119 133
A465 Llanvihangel Crucorney 1978–79 518 465 6 8
A470 Llwyncelyn—Glanrhyd 1978–80 614 561 50 55
A470 Storey Arms—Pontardaf 1978–80 694 644 50 55
A470 Coed Cefn Coch 1978–79 698 662 24 27
A470 Cleifion Bridge 1979–81 630 241 376 419
A470 Pont Dolgefeiliau Stages I and II 1979–80 753 669 68 76
A483 Arddleen By-Pass 1979–80 672 433 169 188
A477 Castell Heli Bridge 1978–79 996 846 120 134
Total 21,650 17,518 2,052 2,290
Proposals to Start: Contracts let after 31 October 1979
A470 Dolcorsllwyn—Dolsgallog 1980–82 582 468 523
A470 White Hut to Maes-yr-Helmau 1980–82 788 100 665 744
A487 Maesnewydd Improvement 1979–81 526 81 403 450
A487 Derwenlas—Machynlleth 1980–82 770 80 662 742
A470 Bends at Smithfield Farm, near Builth 1980–82 650 423 472
A470 Cemmaes Road Improvement* 1980–82 554 120 346 387
A487 Morfa Diversion* 1980–82 502 37 432 482
Total 4,372 418 3,399 3,800
* At the time the Estimates were compiled in November 1979 it was assumed the schemes asterisked would start before the end of the last financial year, and would incur the expenditure shown. For various reasons it was not possible to start the schemes before the end of the financial year.