HC Deb 07 February 1980 vol 978 cc341-2W
Mr. Wm. Ross

asked the Secretary of State for Northern Ireland when he now expects work to begin on the Agivey

Accepted tender Estimated expenditure in 1979–80 Estimated expenditure in 1980–81 Total estimated cost
£m. £m. £m. £m.
A1 Felton By-Pass, Stage 2A 1.7 0.6 1.0 1.9
A2 Canterbury By Pass 8.9 3.0 6.0 10.6
A6 Silsoe By-Pass 1.4 0.7 1.0 1.8
A13 Mar Dyke-East of Grays 18.4 1.8 11.0 22.5
A19 Billingham Diversion 1.9 1.3 0.8 2.2
A27 Portsbridge-Broadmarsh Improvement 2.0 1.5 0.8 2.3
A30 Billet Bridge-Avondale Road 0.6 0.3 0.5 1.1
A34 Whitechurch-Litchfield Improvement 2.1 0.6 1.0 2.2
A45 Ipswich By-Pass (Orwell Bridge) 23.6 1.5 9.0 25.5
A47 Swaffham By-Pass 3.4 1.1 2.0 4.2
A56 Haslingden By-Pass 10.8 2.5 6.0 13.3
A66 Stockton-Thornaby 10.4 5.0 6.0 14.0
A66 Appleby By-Pass 6.6 2.7 3.0 7.9
A590 Meathop-Sampool Bridge 6.0 2.5 3.0 7.2
A590 Ulverston Diversion Stage 3 0.8 0.3 0.5 1.0
A604 Bar Hill-Godmanchester 8.1 3.5 4.0 11.2
A629 Skipton By-Passes 10.2 3.0 4.0 12.4
A1079 Beverley By-Pass 8.0 5.0 4.0 10.1
M25 Chertsey-Wisley: New Haw Viaduct 3.7 1.5 1.5 4.2
M25 A111-A10 15.8 6.3 11.0 19.2
M25 Egham-Yeoveney 6.4 4.0 3.0 8.4
M25 A13-A12, Stage 2 7.2 0.8 4.0 8.4
M63 Stockport East/West By-Pass, Stage 2 6.1 3.0 3.0 8.6
M63 Stockport East/West, Stages 4/5 10.7 0.5 5.0 13.2
Notes:
(i) Information relates to schemes estimated to cost more than £0.5m. in the national programme.
(ii) The figures exclude the cost of land.
(iii) Actual expenditure in 1980–81 will depend on future price increases and progress with construction.
(iv) Total estimated cost includes the accepted tender price, an allowance for contingencies, ancillary works (where appropriate) and price increases acceptable under the contract which have already occurred. It does not allow for future inflation.

Mr. Dudley Smith

asked the Minister of Transport for how many English motorways and trunk road construction

bridge across the River Bann; how much it will cost; and how long the work will take.

Mr. Goodhart

Work is expected to begin this month and completion is scheduled for the autumn of this year. The total cost is estimated at £536,000 including £48,600 for temporary bridgeworks.