HC Deb 19 December 1980 vol 996 c399W
Mr. Beith

asked the Secretary of State for the Environment what has been the cost so far of work carried out by his Department on the Pele tower at Edlingham, Northumberland; when the work is expected to be finished; and what the final cost is expected to be.

Mr. Heseltine

This monument was taken into guardianship in November 1975; consolidation work started in the financial year 1976–77.

Financial Year Expenditure (rounded)
£
1976–77 4,000
1977–78 11,500
1978–79 26,000
1979–80 28,000
Total 69,500

The estimated cost of work in the current financial year is £40,000. Consolidation is estimated to be completed in 1991 at a total cost of (1980 prices) £360,000.