§ Mr. Fryasked the Secretary of State for Wales if he will list in the Official Report all motorway and trunk road
ESTIMATED REQUIREMENTS FOR 1979–80 Year of authorisation to year of completion Current estimate of total cost £'000 Probable expenditure to 31 March 1979 £'000 1979 survey prices £'000 Outturn prices £'000 Schemes in progress: Trunk Roads (Contracts let by 31 October 1978) Treffgarne Bridge (0.7 kms.) … 1978–79 785 270 490 549 Cefn Brynich including Cross Roads (1.4 kms) … … 1978–79 707 248 421 473 Castell Heli Bridge (2.0 kms.) … 1978–79 900 366 510 573 Rhiw Bridge (1.6 kms.) … … 1978–79 559 476 9 10 Goytre Hall Diversion (1.9 kms.) 1977–79 627 540 85 95 TOTAL … … … 3,578 1,900 1,515 1,700 Proposals to Start (Contracts let after 31 October 1978) Pontargothi By-pass (1.8 kms.) … 1979–80 502 — 190 213 Western Avenue Stage I Access to Industrial Estate (0.4 kms.) … 1980–81 990 — 108 121 Pont Dolgefeiliau Stages I and II (2.1 kms.) … … … 1978–79 744 100 600 674 White Hut-Maes-yr-Helmau (1.6 kms) … … … … 1979–80 645 — 300 337 Furnace Bridge-Eglwys Fach (2.0 kms.) … … … … 1979–81 734 — 165 185 G S Junction at Aston Hill (1.0 kms.) … … … … 1980–81 865 — 62 70 Total … … … 4,480 100 1,425 1,600