§ Mr. Mackintoshasked the Secretary of State for Scotland what response he intends to make to the application from the South of Scotland Electricity Board for consent to the construction of an advanced gas cooled reactor nuclear power station at Torness, East Lothian.
§ Mr. MillanI have received representations from several organisations and individuals to the effect that there should be further public inquiry into the South of Scotland Electricity Board's application to construct a nuclear power station at Torness in the light of the decision to adopt the advanced gas cooled reactor system in place of the steam generating heavy water reactor system for which the Board have approval at present.
Crossing Responsible Authority 1974–75 1975–76 1976–77 Erskine Bridge … Secretary of State for Scotland … 380,557 417,495 417,743 Forth Bridge … … Joint Board … … … … 1,413,560 1,376,874* 1,587,248 Tay Bridge … … Joint Board … … … … 656,637 600,484* 695,513 * 45 week period 16th May 1975 to 31st March 1976.