§ Mr. Temple-Morrisasked the Secretary of State for Transport if he will list, giving the estimated cost of each, those trunk road schemes which were added to the forward programme during the six months ended 31st March 1978.
§ Mr. William RodgersThe following schemes in England received firm programme approval during the six months ended 31st March 1978:
Estimated Works Cost (November 1977 Prices) £m M25—Yeoveney-Airport Spur 11.2 A17—New Washway Road 2.4 A17—Swineshead By-Pass 1.5 A20—Sidcup By-Pass 22.5 A30—Okehampton By-Pass 9.5 A31—Wimborne By-Pass 3.4 A39—Bideford By-Pass 12.1 A590—Ulverston Diversion Stage 3 0.8