§ Mr. Hicksasked the Secretary of State for Industry when construction of the advance factory at Callington is due to commence; and what is the intended completion date and the size of this factory.
§ Mr. HefferConstruction is expected to start in the late spring of 1975, by which time the land needed should have passed into the Department's possession. The factory, which is 929 square metres—10,000 square feet—should then be completed by the end of 1975.