Scheme Original Estimated Date of Completion* Current Estimated Date of Completion
A465 Abergavenny Bypass December 1974 December 1974
A465 Glynneath Bypass December 1973 April 1974
A465 Aberdulais-Llandarcy November 1973 August 1974
A470 Nantgarw-Glyntaff December 1972 November 1973
A470 Glyntaff-Abercynon December 1973 November 1973
A483 Wrexham Bypass April 1974 December 1973
A470 Doldowlod Improvement March 1974 March 1974
A5 Wilsons Tyre Depot-The Lookout, Bangor October 1973 December 1973
A40 Abbey Mead-Carmarthen May 1974 May 1974
A48 Rhydsarnau Bridge May 1974 May 1974
A55 East of Northop Crossroads to East of Gables March 1974 December 1973
A470 Waterloo Bridge to Rhyd-y-Creua January 1974 January 1974
A487 Pont Dolbenmaen July 1974 July 1974
A477 Nash-Milton House January 1975 January 1975
A487 Vaynol Junction, Port Dinorwic July 1974 July 1974
* The dates given here are the completion dates estimated when work started.