HC Deb 22 December 1972 vol 848 c503W
Mr. MacArthur

asked the Secretary State for Scotland what estimate he has made of the total value of roadworks under the additional public works programme; what yearly expenditure this represents; and how much of this expenditure has been taken up by contracts let to contractors and local authority labour departments.

Mr. Gordon Campbell

The total value of road works under the additional public works programme is estimated at £18.6 million, about one-third of which is attributable to local authority labour departments and about two-thirds to contractors. Expenditure of £1.7 million was incurred in 1971–72; expenditure in 1972–73 is expected to amount to £11.5 million, and in 1973–74 to £5.4 million.

Mr. MacArthur

asked the Secretary of State for Scotland what estimate he has made of the total value of the additional public works programme; and what total yearly expenditure this represents.

Mr. Gordon Campbell

Projects worth a total of £74 million have been approved under the additional public works programme in Scotland, with an estimated annual expenditure of:

1971–72 £3.4 million
1972–73 £46.6 million
1973–74 £24.0 million