HC Deb 11 November 1968 vol 773 cc16-7W
Dame Joan Vickers

asked the Minister of Transport how many miles of road he anticipates will be built in 1969 in the region of the South-West Economic Planning Council; where these will be situated; and when they will be open to the public.

Mr. Marsh

It is estimated that some 73 miles of road will be under construction

Scheme Estimated Completion
PRINCIPAL ROADS
A39—Truro Relief Road Early 1969
A30—New Exe Bridge (Phase 1) Early 1970
A379—Teignmouth Central Area Late 1970
A350—Poole Old Town Overbridge Early 1971
A388/B3242—Plymouth, North Cross Junction Late 1971
Salisbury City Relief Road (Stage 2) Early 1969
Bristol Parkway (Stage 1) Mid 1970
Gloucester Relief Road (Stage 1) Mid 1970
Bristol Inner Circuit Road (Stage 5) Late 1970
TRUNK ROADS AND MOTORWAYS
A38—Cullompton By-pass, Devon Mid 1969
A40—Golden Valley By-pass, Glos. Late 1969
A303—Amesbury By-pass, Wilts. Mid 1969
M5—Filton By-pass to Avon Bridge Late 1969
M5—Eastington to Almondsbury Late 1971
M5—Avon Bridge to St. Georges Late 1972
M5—Strensham to Eastington Spring 1971