HC Deb 30 January 1967 vol 740 cc33-4W
Sir S. Summers

asked the Minister of Transport (1) what was the cost of the M1 up to the end of 1959;

(2) what was the cost, excluding extra telephones and notices, of work on the Ml, south of Crick, in the years 1960 to 1966, respectively.

Mr. Swingler

The total cost of constructing the first 72 miles of M1 and its spur roads, up to 31st December, 1959, was £.30.7 million.

Work done, excluding the new telephone system and extra signs, routine maintenance and administrative expenses, in succeeding years cost:

million
1960 £0.6
1961 £0.15
1962 £0.25
1963 £0.4
1964 £0.9
1965 £2.1

A sum of £1.9 million was estimated for further work in 1966.