HC Deb 19 December 1967 vol 756 c399W
Mr. Lawson

asked the Secretary of State for Scotland what progress has been made with the school-building programme in Scotland this year compared with last.

Mr. Ross:

There has so far been a substantial increase in the value of school-building projects approved and started, as is shown in the table set out below:—

SCHOOL BUILDING IN SCOTLAND
1966 1967
January-November January-November
Value of projects approved in period £l1.3 million £24.8 million
January- October January-October
Value of projects started in period. £14.8 million £23.6 million