§ Sir R. Russellasked the Minister of Transport what plans are complete for further underpasses and flyovers in the Greater London Area; and on what dates construction will be completed.
§ Mr. SwinglerThe following schemes are expected to start by December, 1967:
Trunk Roads Expected Completion A3 Flyover at Coombe Lane End 1968 A3 Underpass at Tolworth Spring 1969 A2 Greenwich Boundary to Dartford Diversion (including four flyovers) Late 1969 A4 Temporary flyover at Burlington Lane Late 1967 A13 Beckton Road diversion —includes grade-separated junction Early 1970 A40 Flyover at Gipsy Corner Early 1970 Classified Roads A2 Bricklayers Arms 1970 A102 Blackwall Tunnel, Southern Approach Late 1969 A217 Wandsworth Bridge Southern Approach Mid 1970