§ Sir E. Erringtonasked the Secretary of State for Defence if he will state the nature of the proposed work and improvements at the Cambridge Hospital, Aldershot, together with their cost and anticipated date of completion.
§ Mr. ReynoldsA new Out Patients Department will be provided and improvements will be made to the Casualty and X-Ray Departments and the wards. The cost will be about £170,000. The98W work is planned to start in February, 1967 and to take about two years to complete.