§ 17. Mr. Hefferasked the Minister of Health what are the reasons for the continued delay in the completion of the new out-patient department at Walton Hospital, Liverpool; and what steps are being taken to speed up the work.
§ Mr. K. RobinsonThe cumulative effects of labour disputes, low productivity and, in the first year, bad weather. Additional supervisory staff has been allocated and a revised programme prepared to co-ordinate the work of the engineering and main contractors.