HC Deb 06 December 1966 vol 737 c291W
Mr. Berry

asked the Minister of Transport if she will list the major road pro-

At time of deferment Actual or Revised
Scheme Target date for start Target date for completion Target date for start Target date for completion Estimated cost at time of deferment
£
1. Holloway Road, Reconstruction of Railway Bridge. September, 1965 May, 1966 September, 1968 September, 1969 157,310
(bridge being redesigned)
2. Barking Road Late 1965 Late 1967 (None: revised scheme now under consideration) 266,047
3. Upper Thames Street (Bush Lane to Arthur Street). November, 1965 November, 1966 13th December, 1966 December, 1967 497,715
4. Finchley Road November, 1965 Mid-1967 4th July, 1966 January, 1968 3,370,000
5. St. John's Hill Late 1965 Late 1966 14th November, 1966 November, 1967 338,800
6. Feltham High Street December, 1965 September, 1966 October, 1966 September, 1967 116,640
7. Heath Road, Twickenham August, 1965 August, 1966 April, 1966 March, 1967 128,496
8. Cowley Road, Uxbridge Late 1965 15 months after start June, 1967 May, 1969 291,200
9. Gunnersbury Station Railway Bridge and Subway. September, 1965 August, 1967 January, 1967 December, 1968 290,818
10. Hall Lane Flyover November, 1965 November, 1966 June, 1966 June, 1967 228,935
11. Beckenham Road Railway Bridge. July, 1965 July, 1966 (None: Details of scheme being reconsidered) 103,000