§ Mr. RedheadThe following primary school building projects have been 171W included in Cornwall's Major Building Programmes over the last five years:
School Size (places) Estimated Cost 1961/62 £ Helston Infants 240 46,679 1962/63 Camborne C.E. aided 160 36,570 Falmouth, Marlborough Infants 160 37,055 1963/64 Constantine County Primary 120 30,934 Helston, Churchfield County Primary 280 58,688 1965/66 Biscovey County Infants 240 51,351 Threemilestone County Primary (instalment) 160 40,469 St. Ives County Infants 240 54,550 1966/67 Helston County Primary 280 60,919 Falmouth, St. Mary's R.C. Primary 120 40,607 In addition, approval was given by the Department for minor works to be undertaken by the managers of aided primary schools as follows:
Year Number of Schools Approximate total cost 1961/62 … … 2 1,179 1962/63 … … Nil Nil 1963/64 … … 6 12,176 1964/65 … … 1 4,368 1965/66 … … 3 6,912 1966/67 … … 5 41,053 Minor works at county and controlled schools are the responsibility of the local education authority: I understand they were undertaken, or are about to be undertaken during the current year, as follows:
Year Number of Schools Approximate total cost 1961/63 … … 6 15,950 1963/64 … … 9 33,400 1964/65 … … 7 28,500 1965/66 … … 6 43,000 1966/67 … … 7 48,600