HC Deb 08 August 1966 vol 733 c283W
Mr. Gresham Cooke

asked the Minister of Transport how many additional miles of motorway will be open to traffic in each of the next five years.

Mrs. Castle

It is impossible to forecast completion dates with any certainty until contracts have actually been let. Forty-eight miles are under construction in England for completion in 1966 and a further 68 for 1967, and I understand from my right hon. Friend the Secretary of State that a further 6¾ miles should be completed in Wales during that year. At present 33¾ miles are under construction for completion in 1968, but I expect this figure to be increased by the letting of further contracts during the remainder of this year. On present plans at least a further 150 miles should be ready by 1970.