§ 78. Mr. W. Baxterasked the Secretary of State for Scotland if he will estimate when the trunk road schemes by-passing Denny and Bonnybridge will be completed.
§ 80. Mr. Benceasked the Secretary of State for Scotland when he expects work will be completed on the trunk road scheme at Cumbernauld.
§ Mr. NobleIn about three of four weeks one carriageway should be open to traffic on the continuous length of the Cumbernauld and Denny by-passes. Both carriageways should be open by October.
The spur road by-passing Bonnybridge and Larbert, on the road to Kincardine Bridge, was started last September. The work is making good progress and will, I hope, be finished within the 2-year contract period.