§ Mr. K. Robinsonasked the Minister of Health what is the aggregate estimated cost of the teaching hospitals' building programmes for the period covered by the latest revision; how this compares with the estimated cost of the programmes at the previous revision; what schemes were suggested as likely to start within the original programmes but are now beyond it and likely to start within the present 10-year programme; and which schemes in the programmes following the first revision have now been deferred beyond 1974.
§ Mr. Barber£169 million; this exceeds the estimated cost at the previous revision by £27 million; none; none; some schemes now differ in scope from what was earlier envisaged, and are likely to change further.