§ Lieut.-Colonel Bromley-Davenportasked the Minister of Transport and Civil Aviation to issue a list of schemes under the road programme costing over £100,000, which were started in the six months ended 31st December, 1956, with estimated completion date and total cost of each.
219W
§ Mr. WatkinsonThe schemes are:
220W
—— Estimated completion date Estimated total cost TUNNEL £ Dartford/Purfleet Tunnel, Kent-Essex 1962 11,129,000 LONDON AND APPROACHES Elephant and Castle, Improvement, Part I (Demolition works) December, 1959 535,000 Notting Hill Gate, Widening, etc. March, 1960 1,853,000 A1/A.41, Mill Hill to Page Street, Middlesex, second carriageway December, 1957 265,000 A.10, Great Cambridge Road, Bury Street-Carterhatch Lane, second carriageway March, 1958 204,000 A.40, Western Avenue, Middlesex, dualling, Alperton Lane-Greenford Railway Bridge December, 1957 279,000 URBAN SCHEMES Billingham, Co. Durham, Saltworks Bridge diversion December, 1958 151,000 Plymouth, Eastern Approach Road, Gasking Street-St. Andrew's roundabout December, 1958 258,000 Christchurch, Hampshire, By-pass February, 1959 452,000 Portsmouth, new road (Cosham) connecting London Road (A.3) and Southampton Road February, 1958 237,000 Sheffield, Inner Ring Road, Section I November, 1958 191,000 TRUNK ROAD SCHEMES A.1, Alconbury Hill to Woolpack Crossroads, Hunts., second carriageway December, 1957 416,000 A.1, Doncaster Mill Bridge, Reconstruction Spring, 1959 475,000 A.1, Sinderby, North Riding, bridge and approaches Spring, 1958 203,000 A.52, Borrowash, Derbyshire, By-pass March, 1958 263,000 A.59, Longton, Lancs., By-pass September, 1957 491,000 A.556, Northwich, Cheshire, By-pass, Western section October, 1959 276,000