§ 71. Wing-Commander Hulbertasked the Minister of Works if he will make a statement in regard to the progress of the rebuilding of the House of Commons Chamber; and if he will give an approximate date when he anticipates the work will be completed.
§ Mr. KeyThe steelwork of the new House of Commons Chamber is three-quarters completed. Work started in March, 1947, on the main building contract, and specialist sub-contracts have been let. Having regard to the difficulties in the supply of building materials and labour, it is too early to forecast with certainty the date when building work will be completed. The contract date is April, 1950, but in present circumstances it is doubtful whether it will be attained. After166W completion of the works contract a period will be necessary for furnishing, and the testing of special equipment.