§ 75. Mr. W. Rossasked the President of the Board of Trade the cost to date of the development of the Kilwinning Industrial Estate; how many factory units have been completed; and how they are presently being used.
§ Mr. BelcherThe amount spent to date on actual development work on the Kilwinning Estate is just over £60,000, to which should be added £3,400 for cost of acquiring the site and £22,500 for cost of actual building to date. A factory block of 30,000 square feet is nearing completion but is not yet ready for occupation.