HC Deb 10 December 1947 vol 445 c217W
Mr. Walkden

asked the Minister of Works what buildings in the Doncaster area at the present time are under construction, nearing completion or conversion for industrial purposes or factory space; and what are the materials in short supply which are causing delay in completion of these buildings.

Mr. Key

There are 13 industrial buildings and factories under construction in the Doncaster area. Their estimated total value is £433,000. Six of them, with an estimated value of £55,000, are nearly completed. In addition, three buildings are being converted for factories at a cost of about £8,000, of which one building is nearing completion. So far as I am aware, only one factory has been delayed by lack of materials, due partly to a shortage of cement which has now been overcome, and partly to delay in securing electrical equipment, in connection with which assistance is being given by my Ministry.