HC Deb 29 March 1945 vol 409 cc1548-50W
Sir G. Mander

asked the Chancellor of the Exchequer if he will state for each year since its inception the total proposals and sums involved, both approved and not approved, with regard to schemes submitted to the Capital Issues Committee.

Sir J. Anderson

The table below gives the approximate figures by years from the outbreak of war to 31st January, 1945.

New Projects Conversions, Replacements, Renewals, Postponements, etc. Grand Totals
Allowed Refused Total Allowed Refused Total Allowed Refused Total
Nos. £'000 Nos. £'000 Nos. £'000 Nos. £'000 Nos. £'000 Nos. £'000 Nos. £'000 Nos. £'000 Nos. £'000
Period
To 31.3.41 3,855 99,873 71 6,391 3,926 106,264 1,514 124,559 79 6,091 1,593 130,650 5,369 224,432 150 12,482 5,519 236,914
1.4.41 to 31.3.42. 1,478 29,156 35 4,548 1,513 33,704 515 150,719 41 1,711 556 152,430 1,993 179,875 76 6,259 2,069 186,134
1.4.42 to 31.3.43. 985 31,525 32 1,646 1,017 33,171 532 123,326 54 8,740 586 132,066 1,517 154,851 86 10,386 1,603 165,237
1.4.43 to 31.3.44. 1,229 40,376 93 8,023 1,322 48,399 558 78,625 78 14,975 636 93,600 1,787 119,001 171 22,998 1,958 141,999
1.4.44 to 31.1.45. 1,123 41,050 114 10,736 1,237 51,786 564 122,103 78 6,674 642 128,777 1,687 163,153 192 17,410 1,879 180,563
Totals 8,670 241,980 345 31,344 9,015 273,324 3,683 599,332 330 38,191 4,013 637,523 12,353 841,312 675 69,535 13,028 910,847