HC Deb 15 November 1988 vol 140 c550W
Mr. Raffan

To ask the Secretary of State for Wales how far the construction of the A55 Northop bypass is ahead of schedule; and when he expects it to be completed.

Mr. Wyn Roberts

The contract completion date for Northop bypass is August 1989. I am advised that the works could be sufficiently advanced to enable the bypass to be opened to traffic in spring 1989. Actual completion is of course, subject to a number of factors not least of which are the weather conditions over the intervening period.