HC Deb 01 April 1976 vol 908 cc527-8W
Mr. Faulds

asked the Secretary of State for the Environment what is the cost of the new M23 from Hooley to just south of Crawley and the M25 from Godstone to Reigate Hill.

Mr. Marks

The present estimated costs, including land, are: M23 Hooley to Pease Pottage—but excluding the section between Merstham and Bletchingley—together with the Gatwick and Crawley Links, about £23 million; M25 Godstone to Reigate, M23/M25 Merstham Interchange and M23 Merstham to Bletchingley, about £18 million. The final land costs will not be known for some years.